电子文档交易市场
安卓APP | ios版本
电子文档交易市场
安卓APP | ios版本

项目管理专业人士资格认证PMP项目集成管理练习120题和答案

21页
  • 卖家[上传人]:plu****55
  • 文档编号:371943590
  • 上传时间:2023-12-08
  • 文档格式:DOC
  • 文档大小:80KB
  • / 21 举报 版权申诉 马上下载
  • 文本预览
  • 下载提示
  • 常见问题
    • 1、项目集成管理1. Empowerment of the project team requires the project manager to provide all of the following except: A. A sense of ownership and belonging B. A detailed project plan C. Direction and leadership D. Common objectives 授权给项目团队要求项目经理提供下列事项但除了A. 拥有和归宿感B. 详细的项目计划C. 指挥和领导D. 共同的目标2. Project managers spend a considerable amount of time communicating and interacting with project stakeholders. Which of the following methods or techniques would be most useful for a project manager to keep the projec

      2、t team focused on project success? A. Analyze the work occasionally to determine what can be eliminated B. Keep the priorities clear C. Schedule the most interesting activities at energy peaks D. When problems arise, transfer blame to the stakeholders 项目经理要花很多时间与项目相关者进行沟通交流下列哪项方法或技术会对项目经理最有用以便项目团队齐心协力使项目成功A. 定期分析工作以决定排除什么事项B. 明确优先事项C. 在精力高峰期安排最有趣的活动D. 当出现问题时责备其它项目相关者3. A project sponsor is required to make important decisions that may impact the future of the project. In helping the sponsor to a

      3、rrive at good decisions, the project manager should A. Withhold information that may be embarrassing to the team or senior management B. Have a wide variety of graphs and table available C. Utilize progress charts with current weeks information only D. Provide timely, accurate and complete data on a regular basis 事关项目未来成败的重要决策要由项目业主决定为了帮助业主作出明智决策项目经理应该A. 隐瞒可能会让项目团队或高层管理难堪的信息B. 充分准备各种图表C. 使用仅表明本周信息的进度图表D. 定期规范地提供准确完整及时的数据资料4. A project manager estimates a project will take 14 weeks at a cost of $

      4、60,000. In signing the contract documents, the customer imposes a penalty for late completion of $2,000 per estimates that the maximum possible crashing of the project duration is 4 weeks, at an additional cost of $9,000. Assuming that the project manager is going to make the decision and that cost is the driving criteria for the project managers organization, what is the expected project cost? A. $69,000 B. $71,000 C. $70,000 D. $62,000 某项目经理估算一项目要花14 周时间成本$60,000 在签合同文件时客户要求延期完工赔偿$2,000 项目工期的最

      5、大可能的赶工时间是4 周附加成本$9,000 假定成本是主要的衡量标准项目经理要作出决策什么是预期的项目成本A. $69,000 B. $71,000 C. $70,000 D. $62,000 5. All of the following processes are part of over all Project Integration Management, except: A. Project Plan Execution B. Project Plan Development C. Schedule Control D. Integrated Change Control 下列事项是整个项目综合管理的一部分除了A. 项目计划执行B. 项目计划开发C. 进度控制D. 整体变化控制6. Core planning processes have clear dependencies that require them to be performed in essentially the same order on most projects. Which of the follo

      6、wing is the correct order as a portion of core planning processes? A. Scope planning, scope definition, activity sequencing, activity duration estimation B. Scope definition, scope planning, activity definition, activity sequencing, activity duration estimation C. Scope planning, scope definition, activity sequencing, activity definition, activity duration estimation D. Activity duration estimation, scope planning, scope definition, activity definition, activity sequencing 核心计划过程有明确的依赖关系在大多数项目中要

      7、以同样的顺序必须完成下列哪一项符合核心计划过程的正确顺序. A. 范围规划-范围定义-活动排序-活动工期估计B. 范围定义-范围规划-活动定义-活动排序-活动工期估计C. 范围规划-范围定义-活动排序-活动定义-活动工期估计D. 活动工期估计-范围规划-范围定义-活动定义-活动排序7. In which project life cycle phase is uncertainty associated with project integration usually the greatest? A. Project executing B. Project planning C. Project closeout D. Project approval 在项目生命周期哪一阶段项目整合的不确定性最大A. 项目执行B. 项目规划C. 项目收尾D. 项目审定8. In making key changes to a project, it is important to have a formal change process and a _ responsible for approvi

      8、ng or rejecting requests. A. Stakeholder B. Change control board C. Subject matter expert D. Project manager 在项目作出重要变更时重要的是要有一个正式的变更过程和一个负责批准或拒绝变更要求的A. 项目相关者B. 变更控制委员会C. 领域事务专家D. 项目经理9. In which project life cycle phase are the risks associated with project integration usually the smallest? A. Project initiation and approval B. Project planning C. Project execution D. Project closeout 在项目生命周期哪一阶段项目整合的风险最小A. 项目立项和审定B. 项目规划C. 项目执行D. 项目收尾10. The most encompassing document to help the project team with project integration activities is the _. A. Project charter B. Project plan C. “As built” report D. Scope change control procedure 能帮助项目团队进行项目整合活动的最完整的文件是A. 项目章程B. 项目计划C. 进程报告D. 范围变更控制流程11. At which level of the Work Breakdown Struct ure is project integration management most costly to perform? A. Level 1 B. Level 2 C. Level 3 D. Level 5 在工作分解结构的哪一层次水平项目综合管理实施代价

      《项目管理专业人士资格认证PMP项目集成管理练习120题和答案》由会员plu****55分享,可在线阅读,更多相关《项目管理专业人士资格认证PMP项目集成管理练习120题和答案》请在金锄头文库上搜索。

      点击阅读更多内容
    最新标签
    信息化课堂中的合作学习结业作业七年级语文 发车时刻表 长途客运 入党志愿书填写模板精品 庆祝建党101周年多体裁诗歌朗诵素材汇编10篇唯一微庆祝 智能家居系统本科论文 心得感悟 雁楠中学 20230513224122 2022 公安主题党日 部编版四年级第三单元综合性学习课件 机关事务中心2022年全面依法治区工作总结及来年工作安排 入党积极分子自我推荐 世界水日ppt 关于构建更高水平的全民健身公共服务体系的意见 空气单元分析 哈里德课件 2022年乡村振兴驻村工作计划 空气教材分析 五年级下册科学教材分析 退役军人事务局季度工作总结 集装箱房合同 2021年财务报表 2022年继续教育公需课 2022年公需课 2022年日历每月一张 名词性从句在写作中的应用 局域网技术与局域网组建 施工网格 薪资体系 运维实施方案 硫酸安全技术 柔韧训练 既有居住建筑节能改造技术规程 建筑工地疫情防控 大型工程技术风险 磷酸二氢钾 2022年小学三年级语文下册教学总结例文 少儿美术-小花 2022年环保倡议书模板六篇 2022年监理辞职报告精选 2022年畅想未来记叙文精品 企业信息化建设与管理课程实验指导书范本 草房子读后感-第1篇 小数乘整数教学PPT课件人教版五年级数学上册 2022年教师个人工作计划范本-工作计划 国学小名士经典诵读电视大赛观后感诵读经典传承美德 医疗质量管理制度 2 2022年小学体育教师学期工作总结
    关于金锄头网 - 版权申诉 - 免责声明 - 诚邀英才 - 联系我们
    手机版 | 川公网安备 51140202000112号 | 经营许可证(蜀ICP备13022795号)
    ©2008-2016 by Sichuan Goldhoe Inc. All Rights Reserved.