    • 1、建筑大学毕业设计外文文献及译文外文原文Study on Human Resource Allocation in Multi-Project Based on the Priority and the Cost of ProjectsLin Jingjing , Zhou GuohuaSchoolofEconomics and management, Southwest Jiao tong University ,610031 ,China Abstract-This paper put forward the affecting factors of projects priority. which is introduced into a multi-objective optimization model for human resource allocation in multi-project environment . The objectives of the model were the minimum cost loss due to the delay of the

      2、 time limit of the projects and the minimum delay of the project with the highest priority .Then a Genetic Algorithm to solve the model was introduced. Finally, a numerical example was used to testify the feasibility of the model and the algorithm. Index TermsGenetic Algorithm, Human Resource Allocation, Multi-projects projects priority .1. INTRODUCTIONMore and more enterprises are facing the challenge of multi-project management, which has been the focus among researches on project management.

      3、In multi-project environment ,the share are competition of resources such as capital , time and human resources often occur .Therefore , its critical to schedule projects in order to satisfy the different resource demands and to shorten the projects duration time with resources constrained ,as in 1.For many enterprises ,the human resources are the most precious asset .So enterprises should reasonably and effectively allocate each resource , especially the human resource ,in order to shorten the

      4、time and cost of projects and to increase the benefits .Some literatures have discussed the resource allocation problem in multi-project environment with resources constrained. Reference 1 designed an iterative algorithm and proposed a mathematical model of the resource-constrained multi-project scheduling .Based on work breakdown structure (WBS) and Dantzig-Wolfe decomposition method ,a feasible multi-project planning method was illustrated , as in 2 . References 3,4 discussed the resource-cons

      5、trained project scheduling based on Branch Delimitation method .Reference 5 put forward the framework of human resource allocation in multi-project in Long-term ,medium-term and short-term as well as research and development(R&D) environment .Based on GPSS language, simulation model of resources allocation was built to get the projects duration time and resources distribution, as in 6. Reference 7 solved the engineering projects resources optimization problem using Genetic Algorithms. These lite

      6、ratures reasonably optimized resources allocation in multi-project, but all had the same prerequisite that the projects importance is the same to each other .This paper will analyze the effects of projects priority on human resource allocation ,which is to be introduced into a mathematical model ;finally ,a Genetic Algorithm is used to solve the model. 2. EFFECTS OF PROJECTS PRIORITY ON HUMAN RESOUCE ALLOCATION AND THE AFFECTING FACTORS OF PROJECTS PRIORITYResource sharing is one of the main cha

      7、racteristics of multi-project management .The allocation of shared resources relates to the efficiency and rationality of the use of resources .When resource conflict occurs ,the resource demand of the project with highest priority should be satisfied first. Only after that, can the projects with lower priority be considered.Based on the idea of project classification management ,this paper classifies the affecting factors of projects priority into three categories ,as the projects benefits ,the

      8、 complexity of project management and technology , and the strategic influence on the enterprises future development . The priority weight of the project is the function of the above three categories, as shown in (1). W=f(I,c,s) (1)Where w refers to projects priority weight; I refers to the benefits of the project; c refers to the complexity of the project, including the technology and management; s refers to the influence of the project on enterprise .The bigger the values of the three categori

      9、es, the higher the priority is.3. HUMAN RESOURCE ALLOCATION MODEL IN MULTI-PROJECT ENVIRONMENT3.1 Problem DescriptionAccording to the constraint theory, the enterprise should strictly differentiate the bottleneck resources and the non-bottleneck resources to solve the constraint problem of bottleneck resources .This paper will stress on the limited critical human resources being allocated to multi-project with definite duration times and priority.To simplify the problem, we suppose that that three exist several parallel projects and a shared resources storehouse, and the enterprises operation only involves one kind of critical human resources. The supply of the critical human resource is limited, which cannot be obtained by hiring or any other ways during a certain period .when resource conflict among parallel projects occurs, we may allocate the human resource to multi-project according to projects priorities

      《建筑外文文献及翻译》由会员jiups****uk12分享,可在线阅读,更多相关《建筑外文文献及翻译》请在金锄头文库上搜索。

      点击阅读更多内容
    最新标签
    信息化课堂中的合作学习结业作业七年级语文 发车时刻表 长途客运 入党志愿书填写模板精品 庆祝建党101周年多体裁诗歌朗诵素材汇编10篇唯一微庆祝 智能家居系统本科论文 心得感悟 雁楠中学 20230513224122 2022 公安主题党日 部编版四年级第三单元综合性学习课件 机关事务中心2022年全面依法治区工作总结及来年工作安排 入党积极分子自我推荐 世界水日ppt 关于构建更高水平的全民健身公共服务体系的意见 空气单元分析 哈里德课件 2022年乡村振兴驻村工作计划 空气教材分析 五年级下册科学教材分析 退役军人事务局季度工作总结 集装箱房合同 2021年财务报表 2022年继续教育公需课 2022年公需课 2022年日历每月一张 名词性从句在写作中的应用 局域网技术与局域网组建 施工网格 薪资体系 运维实施方案 硫酸安全技术 柔韧训练 既有居住建筑节能改造技术规程 建筑工地疫情防控 大型工程技术风险 磷酸二氢钾 2022年小学三年级语文下册教学总结例文 少儿美术-小花 2022年环保倡议书模板六篇 2022年监理辞职报告精选 2022年畅想未来记叙文精品 企业信息化建设与管理课程实验指导书范本 草房子读后感-第1篇 小数乘整数教学PPT课件人教版五年级数学上册 2022年教师个人工作计划范本-工作计划 国学小名士经典诵读电视大赛观后感诵读经典传承美德 医疗质量管理制度 2 2022年小学体育教师学期工作总结
     
    收藏店铺
    关于金锄头网 - 版权申诉 - 免责声明 - 诚邀英才 - 联系我们
    手机版 | 川公网安备 51140202000112号 | 经营许可证(蜀ICP备13022795号)
    ©2008-2016 by Sichuan Goldhoe Inc. All Rights Reserved.