引水隧洞工程开挖施工工法.doc
13页xx. 水城 xxx 水电站引水隧洞工程开挖施工工法(合同编号: MJH/A-3)批准:审查:校核:编写:广东 xxx局股份有限公司xxx 水电站引水隧洞工程项目部二〇xx 年二月四日- 1 -目录1编制依据及目的 .............................................................................................................................- 3 -1.1编制目的 ............................................................................................................................- 3 -1.2编制依据 ............................................................................................................................- 3 -2适用范围 .........................................................................................................................................- 3 -3施工准备 .........................................................................................................................................- 3 -3.1洞口明挖地段 ....................................................................................................................- 3 -3.2洞身开挖 ............................................................................................................................- 4 -4施工方法及工艺要求 .....................................................................................................................- 4 -4.1洞口明挖地段 ....................................................................................................................- 4 -4.2隧洞洞身开挖一般要求 ....................................................................................................- 6 -4.3隧洞洞身开挖主要方法 ....................................................................................................- 7 -5隧洞钻爆开挖设计及钻爆作业.....................................................................................................- 7 -5.1一般规定 ............................................................................................................................- 8 -5.2炮眼布置应符合下列规定: ............................................................................................- 8 -5.3爆破参数选择 ....................................................................................................................- 8 -5.4Ⅲ级和Ⅳ级围岩光面爆破施工工艺................................................................................- 9 -5.5钻爆作业施工质量控制 ..................................................................................................-10-5.6爆破技术措施 ...................................................................................................................-11-5.7要求: ................................................................................................................................-11-6隧洞开挖安全技术措施 ...............................................................................................................-12-6.1安全保证措施 ...................................................................................................................-12-1.6.2 安全技术措施 ...............................................................................................................-12-6.3隧洞支护安全措施 ..........................................................................................................-13-- 2 -引水隧洞开挖施工工法1 编制依据及目的1.1 编制目的指导开挖作业人员进行 xxx 水电站工程引水隧洞施工支洞及隧洞洞口明挖、 洞身开挖施工。
1.2 编制依据北盘江 xxx 水电站工程《 2009 年度达标投产考核实施细则》 水电站引水隧洞工程施工招标文件(合同编号: MJH/A-3) 水工建筑物地下开挖工程施工规范( SL378-2007) 水电水利工程爆破施工技术规范( DL/T 5135-2001 )2 适用范围2.1xxx 水电站工程引水隧洞施工支洞洞口段明挖施工2.2xxx 水电站工程引水隧洞施工支洞及隧洞洞身段开挖施工2.3 隧洞开挖施工, 其中分部开挖适用于Ⅳ级、 Ⅴ级围岩, 全断面开挖法适用于Ⅱ、Ⅲ级围岩开挖施工2.4 隧洞爆破施工作业3 施工准备3.1 洞口明挖地段认真学习设计图纸, 了解设计意图, 深入工地做好施工调查、 核对设计文件,调查核对工程地质、边坡是否符合实际结合设计图纸和施工方案进行测量放线,确定洞门的平面位置、几何尺寸和地面高程等,结合放坡开挖的坡度、坑底水沟的设置确定开挖的尺寸 3 -进行钻爆设计,内容包括炮眼的布置、深度、斜率和数目,爆破器材、装药量和装药结构,起爆方式和爆破顺序,钻眼机具和钻眼要求等钻爆设计图应包括炮眼布置图、周边眼装药结构图、钻爆参数表、主要经济技术指标及必要的说明。
检查边坡以上的山坡稳定情况,消除悬石、处理危石进行洞口截水边沟的施工,并确保水流畅通3.2 洞身开挖超前地质预报:采用地质超前预测预报系统对前方围岩进行超前探测,分析围岩的各种性能指标,以确定合理的施工方案施工测量放样:开挖前将控制开挖的中线、水平引至开挖部位掌子面,确定开挖轮廓根据钻爆设计布置好炮眼钻爆设计:岩石隧洞开挖前,根据工程地质条件、开挖断面、开挖方法、掘进循环进尺、钻眼机具和爆破材料等进行钻爆设计其内容为:炮眼的布置、深度、斜率和数目,爆破器材、装药量和装药结构,起爆方式和爆破顺序,钻眼机具和钻眼要求等钻爆设计图应包括炮眼布置图、周边眼装药结构图、钻爆参数表、主要经济技术指标及必要的说明开挖作业照明安装,钻眼机具到位,高压风、水管的连接做好洞内、外排水系统,保证排水畅通规划弃碴位置,布置出碴路线,出碴设备准备4 施工方法及工艺要求4.1 洞口明挖地段施工工序:施工准备 测量放线 边坡开挖 边坡支护开挖施工- 4 -土石方开挖采用从上至下分段分层开挖;分层高度一般为 3-4m,分段长度可按20~30m为宜边坡应随开挖的分层高度随挖随支护 支护类型应根据地质条件和边坡的稳定情况选择,采用素喷或锚网喷支护。
土方开挖方法:人工预先清除。