电气部分系泊试验大纲_图文.docx
46页CONTENTS (目录) 02一、 GENERAL 07总则二、 MOORING TRIALS(ELECTRICAL PART) 07电气部分系泊试验1. Test of diesel gen sets test 08柴汕发电机组试验2. Main switchboard test 1.4主配电板试验3. Emergency generator set test 17应急发电机组试验4. Emergency switchboard test 19应急配电板的试验5. CHP and Battery group test 20充放电板及蓄电池纽的试验6. Test of Steering gear 21舵机试验7. Rudder angle indicator 22舵角指示器8. Measure the insuiation resista nee of power system at hot state 23测最电力系统热态绝缘9. Test of windlasses 23锚机试验10. Test of mooring winches23 系泊绞车试验11. Motor and controller 24电动机及控制器试验12. Transformer test 24变压器试验13. Linghting Equipmcnt 25照明设备The performance test of general UPS26通用UPS效用试验Main eng inc remote con trol system test26主机遥控系统试验Telegraph system test28午钟运行试验E/R automation system test28机舱自动化项H试验Eire-fighting system tost30灭火系统试验Water fire extinguishing system test30水灭火系统试验C02 system test.30二氧化碳灭火系统试验E/R local pressure water mi st system test30机舱水雾灭火系统试验The test of smoke detection system31抽烟式报警系统试验The test of fire alarm system31固定式探火和失火报警系统试验防海生物试验Provision Re.plant test32冷藏装置试验Air conditionpl ant test33Anfomati c system test32空调装置试验Intor communicationsystem test33船内通讯系统试验1 SOUND-POWERED TELEPHONE声力33342 Auto telephone and public adress system22.3tl动及广播系统Signal bell system3422.4信号铃系统Master clock system34子母钟系统23. Radio communication equipment35无线电通信设备23. 1 ME/11F radio communication equipment3523.2中/高频无线电台TWO-WAY radiotelephone (GMDSS handset)3623.3对讲机(GMDSS)VHF radiotelephone3623.4VHF无线EPIRB3723.5]J.星紧急无线电示位标Weather facsimile receiver3723.6气象机Ship earth station (Tnm・ F, Tnm. C)3723. 7卫通地球F站、C站Neivtex receiver3823.8航行告警接收机Community antenna3823.9共用天线Search and rescue radar transponder38雷达应答器24. NAVIGATION EQUIPMENT39航行设备24. 1 Gyro compass3924.2电罗经Magnotic compass39磁罗经24. 3Auto pilot4024.4自动舵Echo sounder4024.5测深仪Speed log4124.6计程仪Radar and ARPA device4124. 7雷达带ARPA装置DGPS receiver4324.8DGPS接收机Cl ear view screen and Electric-heating glass4324.9雨雪清除器及电加热玻璃Wiper4324. 10雨刮器Whistle4324. 11汽笛Anemometer4424. 12风速风向仪VDR4424. 13VDR航行数据记录仪ATS44ATS自动识别仪25. SEA SECURITY EQUIPMENTS44航海安全设备25. 1SSAS (Ship Security Alert system)4425. 2防海盗系统Watertight door open alarm system4525.3水密门开报警系统Water ingress alarm system for cargo hold4525.4货舱进水报警系统Refrigerator cal 1 system 45冷库呼叫系统25. 5 Hospi tal call system 45病房呼叫系统一、GENERAL 总则1. This program is made according to following:本试验人纲根据如下依据编写:a: Chirm national stanckiTd "GB3471T995" (General program for dock and sea trails of diesel engine driven sea going ships)国家标准GB3471-1995 “柴汕机动力海洋船舶系泊及航行试验通则”b: Relevant requirements from BV Rules.试验相关要求根据“BV”要求。
c: Relevant requirements from specification.全船说明书相应要求d: Relevant requirements from makers.设备厂家冇关要求2. Purpose for tests 试验目的:According to this program, inspect and check building quality of the vessel. The technical documents and information shall be subimttcd to the supervisor of owner.通过大纲规定的各项试验,对本船的设计和建造质量进行全面检查和验收,为交船提供必要的技术 文件和资料3. Test items试验内容:Tests shall be done according to this program.按系泊试验大纲4. Test organization for test 试验组织:Tests shall be executed by shipyard. The yard shall give notices to class surveyor and supervisor of owner and design department if necessary. During the test, records shal1 be made and treated for relevant technical documents which to be submit ted to class surveyor and owner. Maker will attend the equipment test if necessary.试验以船厂为主,并通知船东参加试验和验收,其小验船部门规定的试验项目,同时通知验船部门 参加,对涉及设计性能的试验项目通知设计单位参加。
对有关设备,必耍时要求厂家代表参加5. Test preparation 试验准备:All measuring instruments are to be duly calibrated by the recognized competent bodies before the tests.试验使川的各利|测试仪器和仪表,应由专门的校验机构校验(在校验合格有效期内)6. The ships buoyancy and stability see ''Estimated table of Dock and Sea Trial Ballast and Stabi1ity〃.试验时船舶浮态及稳性参照“航行试验的压载及稳性估算表”二,MOORING TRIALS (ELECTRICAL PART)电气部分系泊试验1. Test of diesel gen sets test柴油发电机组试验1. 1 Description of diesel gon sets柴油发电机规格Main electrical generator Description主发电机参数1QTY数量3 SETS2ENG1NG TYPE柴汕机组型号5L16/243NO. OF CYLINDERS 缸数54CYCLE BORE 缸径160nunL□ENGINE OUTPUT柴汕机输出功率500KW6ENG I NG SPEED 转速1200 r/min7MAX.COMBUSTIONPRESSURE 最大爆发压力170bar8GENERATOR TYPE发电机型号HFC6454-64K9GENERATOR OUTPUT发电机功率440 KW10FREQUENCY发电机频率60 Hz11VOLTAGE发电机电压450V12POWER FACTOR功率因素0.813RATED CURRENT额定电流706A1. 2 Insulation resistance test绝缘电阻试验Before and after the load test, insulation resista nee of the following circuits shall be measured by a 500V megger・发电机负荷试验前和试验麻,用500V兆欧表测量下列回路的绝缘电阻:。