6#楼外墙外保温施工方案(Eps板)-secret.doc

19页
  • 卖家[上传人]:王****
  • 文档编号:299331295
  • 上传时间:2022-05-27
  • 文档格式:DOC
  • 文档大小:304.54KB
  • / 19 举报 版权申诉 马上下载
  • 文本预览
  • 下载提示
  • 常见问题
    • 目 录1 工程概况··················································· 22 施工前准备················································· 22.1施工条件················································ 22.2原材料要求·············································· 22.3主要施工工具············································· 43 施工工序··················································· 44施工方法和技术措施········································· 54.1外墙外保温基本构造······································· 54.2基层处理················································ 54.3材料准备 ··············································· 64.4保温层施工··············································· 64.5保护层施工·············································· 145 成品保护措施和修补········································ 156 工程检查验收················································167安全技术措施··············································· 16 1工程概况工程名称:呼和浩特市富升帝豪住宅小区5#、6#住宅楼建设单位:内蒙古库布齐房地产开发有限公司建筑面积:18114。

      39m2(5#楼10073.88 m2)建筑层数:地上十八层;地下三层(5#楼地上22层;地下三层)建筑高度:57.6m(5#楼69.6m)结构类型:剪力墙结构防火等级:一级抗震设防烈度:八度2施工前准备2.1 施工条件2.1.1外墙和外门窗口施工及验收完毕,基面应坚实平整,墙体不应有预留空洞和设置脚手眼,清除其他有碍于施工的杂物2.1.2 EPS(聚苯板)外保温墙体工程施工环境温度和基层墙体表面温度不得低于5℃,风力不大于5级,雨天严禁施工.2.1.3 施工现场应作到通水、通电,并保持工作环境的清洁2.2 原材料要求2.2.1工程所用各种原材料必须按施工规范要求提供相应文件,并经过指定的质量检测部门进行试化验,不合格材料不得进入施工现场2.2.2根据高层建筑外墙EPS外保温工程需要,对EPS板、EPS板、耐碱玻纤网格布、粘结胶浆和抹面胶浆及机械锚固件技术要求如下:(本工程外墙外保温采用聚苯板(EPS) ;只用飘窗部位采用挤朔聚苯板XPS )2.2.2.1 EPS板、XPS板:其性能指标除应符合表1的要求.表1:聚苯板(EPS)、挤塑板(xps)板技术指标 2.2.2耐碱玻璃纤维网格布的主要性能指标应符合表2的要求。

      表2 耐碱玻璃纤维网格布技术指标试验项目单位性能指标标准网格布加强网格布标准网眼尺寸mm4.0—6.05.0—10.0单位面积质量g/m2≥160≥290耐碱断裂强力(经、纬向)N/50mm≥900≥1500耐碱断裂强力保留率(经、纬向)%≥75≥75断裂应变(经、纬向)%≤4.0≤402.2.2.3胶粘剂的主要性能指标应符合表3的要求表3 胶粘剂技术指标检验项目单位性能指标拉伸粘结强度(与水泥砂浆粘结)原强度Mpa≥0.60耐水(48h)≥040拉伸粘结强度(与EPS板粘结)原强度Mpa≥0.20耐水(48h)≥020可操作时间h1.5-4.02.2.2.4抹面胶浆主要性能要求见表4. 表4 抹面胶浆主要技术指标检验项目标准要求拉伸粘结强度(与EPS板粘结)mpa原强度≥020耐水≥0.20耐冻融≥020柔韧性抗压强度、抗折强度(水泥基)≤3.0开裂应变(非水泥基)≥150可操作时间h15-4.02.2.2.5界面剂:必须与所用的保温板配套,由外保温系统供应商全套供应配套材料和技术措施.2.2.2.6机械锚固件:采用的塑料钉和带圆盘的塑料膨胀套管应用聚酰胺、聚乙烯或聚丙烯等材料制成。

      锚栓有效锚固深度不小于25mm,塑料圆盘直径不小于50mm,其单个锚栓抗拉承载力标准值不小于02.3 主要施工工具不锈钢抹子、槽抹子、搓抹子、角抹子、电动搅拌器、专用锯齿抹子、不锈钢打磨抹子、冲击钻、靠尺、刷子、多用刀、灰浆托板、拉线、弹线墨盒、开槽器、电热丝切割器等一般施工工具及操作人员必需的劳动保护用品.3施工工序材料及工具准备基层墙体处理测量、弹线基层墙面湿润安装首层托架(贴面砖时)配制胶粘剂刷界面剂粘贴翻包玻纤网格布 ———--粘贴EPS板安装锚固件做装饰线条EPS板打磨找平特殊部位处理铺加强网、门窗口网布标准网布、起终端翻包网布配制抹面砂浆抹底层抹面胶浆铺贴玻纤网格布护角条施工抹面层抹面胶浆 涂料或面砖 检查及验收4施工方法及技术措施4.1 EPS外墙外保温系统基本构造见下图 4.2基层处理4.2.1结构墙体基面应坚实平整,必须清理干净,无油污、浮尘、脱模剂、涂料、风化物、防水剂等污染物或其它有碍粘结的物质,并剔除表面凸物、空鼓和疏松部位,用聚合物砂浆找平,使之清洁平整 结构墙体平整度较差时,必须进行基层整体找平处理。

      外墙保温粘贴前应对基层进行检查.4.2.2墙体基面的允许尺寸偏差见表5表5  墙体基面的允许尺寸偏差工程做法项目允许偏差≤mm混凝土工程整体找平层垂直度层高≤10m8>10m10全高H/1000且≤30表面平整2m长度54.3 材料准备4.3.1配制胶粘剂打开建筑粘结胶粉末包装袋,把内衬塑料袋剪开袋,将该粉末倒入容器中,然后按照使用说明加入适量水,用手提式搅拌器把胶液搅拌均匀,边加水边搅拌,呈均匀胶泥状后,即可使用(用于EPS板外保温墙体系统的粘贴,EPS板的粘结胶粘剂和抹面胶浆)根据施工手感调整加水量,胶浆的配制应本着一次用多少配多少的原则,随用随搅拌,一次配量以2小时内用完为宜4.3.2 板材的切割应尽量使用标准尺寸(600mm×1200mm)的EPS板,需使用非标准尺寸板时,应采用电热丝切割器切割整齐,大小面垂直,并用砂纸打磨4.3.3耐碱玻纤网格布的准备应根据施工面的需求剪裁网格布,并注意搭接部位预留出足够的搭接长度4.4保温层施工4.4.1弹线:根据设计图纸要求,首先沿着基层墙体散水标高弹好距散水标高20mm的水平线、确定EPS板粘贴模数,并且由下而上,自左至右来确定每排板应上、下错缝,其宽度应为1/2板长;在墙面弹出外门窗水平、垂直控制线及伸缩缝线、装饰线等。

      4.4.2挂基准线:在建筑外墙阳角、阴角及其它必要处挂垂直基准线,每个楼层适当位置挂水平线,以控制粘贴的EPS板的垂直度和平整度4.4.3粘贴翻包网格布:凡在粘贴的EPS板侧边外露处(如伸缩缝、两侧,门窗洞口、勒脚、阳台、雨蓬等系统终端部位,女儿墙顶)见图43-1,2,3,4,都应做玻纤网格布翻包处理4.4.4粘贴板材4.4.4.1外保温用EPS板标准尺寸600mm×1200mm,非标准尺寸可现场裁切,但切口应与板面垂直.整个墙面的边角处应用最小尺寸超过300mm的EPS板EPS板的拼缝不得正好留在门窗口的四角处洞口四角处EPS板应采用整块EPS板切割成形,不得拼接,接缝距离四角距离应大于200mm,且须有锚固措施,并应在洞口四角处加贴一块长300mm,宽200mm的45º斜向标准网格布 4.4.4.2粘贴EPS板采用满粘法:胶粘剂应涂抹在板上,板侧边不得涂胶在板上涂抹粘结胶浆,厚度不小于10mm,压实厚度应控制在3~5mm,粘好后应立即刮除板缝和板侧面残留的胶粘剂每块板与基层墙体粘结面积应保证不小于80%.4.4.4.3排板时按水平顺序排列,上下错缝粘贴,错缝宽度为1/2板长,阴阳角处做错茬处理(见图4。

      45—3)板涂胶后应及时粘贴,粘板应用专用工具轻揉滑动就位、均匀挤压EPS板,不得局部用力按压,EPS板对头缝应挤紧,并与相邻板齐平,胶粘剂的压实厚度宜控制在3-5mm,随时用2m靠尺和托线板检查平整度和垂直度粘板时注意清除板边溢出的胶粘剂,使板与板之间无“碰头灰”板缝不应大于1.5mm,缝宽超出15mm时应采用阻燃型聚氨酯发泡胶填充拼缝高差不大于15mm,否则应用砂纸或专用打磨机具打磨平整粘贴上墙后的EPS板应静置至少24h后,才可打磨,打磨后清除表面漂浮颗粒和灰尘,随时清理干净.4.4.6锚固件固定本工程采用机械锚固件固定EPS板时,锚固件安装应至少在胶粘剂使用24h后进行.用冲击钻在EPS板表面向内打孔,孔径视锚固件直径而定,进墙深度不小于25mm一般钻头直径为8-10mm,拧入或敲入锚固钉,钉头和园盘不得超出板面,锚固钉帽为50mm的锚钉,数量为楼标高在50m以下的4-6个/m2,考虑一层至三层装饰面层外要粘贴面砖,故锚固件按照不少于6个/m2设置,以确保牢固4.4.7防火隔离带 当建筑高度在30m(或10层以上时),每一层做一通长连续(包括山墙)的防火隔离带,采用300宽A级防火岩棉板做为防火隔离带材料。

      防火高度为窗上口至上一层楼板标高处4.5保护层施工4.5.1做保护层施工必须在EPS板面粘贴完毕24h,并且经过打磨找平之后进行施工前应检查板是否干燥,并清扫板面上灰尘及附着物,EPS板要检查平整度4.5.2抹底层抹面胶浆:在板面上抹底层抹面胶浆,厚度2-3mm同时将翻包网格布、标准和加强网格布、成品塑料护角条和滴水线条压入胶浆中4.5.3翻包标准网施工步骤:4.5.3.1裁剪窄幅标准网,长度由需翻包的墙体部位尺寸而定4.5.3.2在基层墙体上所有洞口周边及系统起、终端处,涂抹宽度100mm,厚度约为2mm胶结剂.4.5.3.3将窄幅标准网的一端100mm压入胶粘剂内,余下的另一端甩出备用,并应保持清洁.4.5.3.4将EPS板的背面涂抹好胶粘剂,将其压在墙上,然后用抹子轻轻拍击,使其与墙面粘结牢固.4.5.3.5将翻包部位的EPS板的正面和侧面均涂抹上抹面胶浆,将预先甩出的窄幅标准网沿板厚翻包,并压入抹面胶浆内,当需要铺设加强网时,则应先铺设加。