张家庄隧道实施性施工组织设计(终).doc
121页中交一航局兰新铁路(甘青段)项目经理部一工区 张家庄隧道实施性施工组织设计新建兰新铁路(甘青段)LXS-3 标项目经理部一工区张家庄隧道实施性施工组织设计张家庄隧道实施性施工组织设计编制: 复核: 审核: 2010 年 05 月 09 日中交一航局兰新铁路(甘青段)项目经理部一工区 张家庄隧道实施性施工组织设计1目目 录录1.编制依据∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙1 2.编制范围∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙1 3.工程概况、主要工程数量及施工条件∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙1 3.1.主要技术标准............................................................1 3.2 工程概况................................................................1 3.3 主要工程数量............................................................2 3.4 自然地理特征............................................................2 3.5 工程特点、工程重点、工程难点及相应对策..................................3 4.施工总体方案∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙4 4.1 施工组织机构及施工队伍的分布............................................5 4.2 临建工程布置及总体设计..................................................7 4.3 施工用电................................................................8 4.4 施工用水................................................................8 4.5 施工测量、试验..........................................................9 4.6 内业资料管理(收集、整理、归档、移交).................................12 4.7 施工程序...............................................................12 5.主要施工方案、施工方法、施工工艺及技术组织措施∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙13 5.1 施工方案综述...........................................................13 5.2 正洞施工总体方案.......................................................13 5.3 施工方法、施工工艺.....................................................14 6.总工期及进度计划安排、资金使用计划∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙74 6.1 总工期.................................................................74 6.2 施工进度安排...........................................................75 6.3 资金使用计划...........................................................75 7. 主要材料、工程设备的使用计划和供应方案及措施∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙75 7.1 主要材料...............................................................75 7.2 主要设备...............................................................77 8.创优规划和质量保证措施∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙79 8.1 创优规划...............................................................79 8.2 质量保证体系...........................................................79 8.3 成立质量管理机构.......................................................79 8.4 完善质量管理制度.......................................................83 8.5 质量保证措施...........................................................89 8.6 预防质量通病的措施.....................................................97 9.安全保证措施∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙97 9.1 洞口设调度室...........................................................97 9.2 选派有经验人员到施工现场...............................................98 9.3 建立专门针对隧道施工的制度措施.........................................98 9.4 安全保证体系...........................................................99 9.5 职业健康安全保证措施...................................................99 10.工期保证措施∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙102 10.1 工期目标.............................................................102 10.2 工期保证体系.........................................................102中交一航局兰新铁路(甘青段)项目经理部一工区 张家庄隧道实施性施工组织设计210.3 组织保证措施.........................................................103 10.4 制度保证措施.........................................................103 10.5 技术保证措施.........................................................104 10.6 设备物资保证措施.....................................................104 10.7 劳动力保证措施.......................................................104 10.8 后勤保证措施.........................................................104 11.环保、水保、文物保护措施∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙105 11.1 环境管理.............................................................105 11.2 文明施工措施.........................................................107 11.3 地下管线及文物保护措施...............................................108中交一航局兰新铁路(甘青段)项目经理部一工区 张家庄隧道实施性施工组织设 计1张家庄隧道实施性施工组织设计张家庄隧道实施性施工组织设计1.1.编制依据编制依据⑴ 国家、铁道部和地方政府(省、直辖市)的有关政策、法规和条例、规定;⑵ 国家和铁道部现行设计规范、施工指南、验收标准;⑶ 现行铁路施工、材料、机具设备等定额;⑷ 承发包合同、招投标文件;⑸ 兰新铁路甘青段新建工程第 LXS-3 标张家庄隧道施工图及相关设计文件;⑹ 我项目经理部有关现场踏勘调查资料,水文地质调查资料;⑺ 我单位从事铁路工程中积累的施工经验、技术总结等成果,及我公司现有的施工力量和机械设备、装备情况;⑻ 其它相关依据。
2.2.编制范围编制范围新建兰新铁路第二双线甘青段 LXS-3 标段张家庄隧道洞身开挖、支护、仰拱及填充、二衬、附属设施等施工3.3.工程概况工程概况、主要工程数量及施工条件、主要工程数量及施工条件3.1.3.1.主要技术标准主要技术标准铁路等级:国铁Ⅰ级正线数目:双线线间距:5m纵坡坡度: 3.5‰旅客列车速度目标值: 200 公里/小时曲线半径:。