建筑外墙面砖及外墙高级涂料方案.doc
15页目 录一.工程概况 ............................................................................................................1二.材料及设备 ........................................................................................................11.瓷砖粘结干粉剂 ...............................................................................................12.瓷砖填缝剂 .......................................................................................................13.面砖 ...................................................................................................................24.高级外墙涂料 ......................................................................................................35.弹性腻子 ...........................................................................................................36.设备 ...................................................................................................................3三、施工部署 ............................................................................................................41、进度计划 ...........................................................................................................42、作业队伍 ...........................................................................................................43、样板制度 ...........................................................................................................44、垂直运输 ...........................................................................................................55、施工机械 ...........................................................................................................56、技术质量措施 ...................................................................................................5四.作业条件 ............................................................................................................6五.外墙面砖及外墙高级涂料工艺流程 ................................................................7六.外墙面砖基层处理、弹线分格 ........................................................................7七.外墙面砖排砖 ....................................................................................................7八.外墙面砖施工工艺 ............................................................................................9九.外墙涂料基层处理 ..........................................................................................10十.补腻子 ..............................................................................................................10十一.满刮弹性腻子 ..............................................................................................10十二.刷高级外墙涂料 ..........................................................................................11十三.质量保证措施 ..............................................................................................121.质量要求 ............................................................................................................122.质量管理措施 ....................................................................................................12十四.成品保护措施 ..............................................................................................13十五.安全技术要求 ..............................................................................................131一.工程概况本工程为卓达太阳城花园洋房工程,位于石家庄市栾城县治河镇工贸小区卓达太阳城内。
外墙部分墙面装修做法为粘贴外墙面砖和外墙高级涂料基层均为后粘贴保温板本工程的外墙面砖颜色为浅红色,涂料颜色为:浅灰色、浅黄色、深蓝灰色本工程的外墙面砖颜色一致,颜色为浅红色面砖规格为230mm×53mm面砖为横向交错粘贴,其中窗顶为竖向平排铺贴缝宽为 8mm~10mm二.材料及设备1.瓷砖粘结干粉剂由于本工程采用的是外墙外保温,为保证外墙面砖的粘贴质量,使用专用面砖粘结剂粘贴面砖瓷砖粘结干粉剂使用方法:进场使用时室温下与净水混合每袋干粉需用水 5.5~6 公升,用搅拌机进行搅拌,直到均匀没有结块为止待拌合物静止 5 分钟便可使用搅拌好的瓷砖粘结剂必须在 2 小时内使用粘贴厚度为 7--10mm,平米用量为:12~18 公斤/平方米2.瓷砖填缝剂本工程外墙面砖间缝隙采用专用瓷砖填缝剂,瓷砖填缝剂使用方法:进场使用时室温下与净水混合每袋干粉需用水 5.5~6 公升,2用搅拌机进行搅拌,直到均匀没有结块为止待拌合物静止 5 分钟便可使用搅拌好的瓷砖填缝剂必须在 1.5 小时内使用平米用量为: 5~6 公斤/平方米瓷砖粘结干粉剂与瓷砖勾缝剂均为有关部门鉴定合格的产品,且已经过大量证明效果可靠的产品。
(推荐产品:北京世纪德源装饰材料有限公司的德国艺高牌瓷砖粘结干粉剂与瓷砖填缝剂;天津菲尔特建筑材料有限公司的菲尔特牌瓷砖粘结干粉剂与瓷砖填缝剂)3.面砖 按设计要求外墙贴面砖,规格为 230mm×53mm颜色为浅红色要求面砖必须颜色均匀一致,表面平整,边角方正,厚度一致,不得有缺楞掉角、断裂和隐伤等缺陷几何尺寸一致,吸水率小于1%色泽必须一致内在质量:耐急冷急热于 105---19 度冷热交换一次无裂纹密度在 2.3---2.4g/立方厘米之间硬度 85—87 度几何尺寸允许公差:项目 长度 宽度 厚度公差值 mm ±0.5 ±0.5 +0.3---0.2为了保持面砖颜色一致,所以所选面砖必须为同一批产品,进场时要进行验收,若发现不符合要求的面砖,施工方有权要求退货选3砖方法如下:1、选砖方法:A、 选色:每箱打开后首先选出颜色一致的砖,再装回原箱对颜色不一致的砖要求退货B、 选砖:选出不同的规格的面砖,分别装箱,超出规格为不合格,装好后退场;C、 把厚薄不一的砖分开装箱,分别用在不同的墙面,用镶贴砂浆的厚度来调节砖的厚度D、 设专人保管和发放4.高级外墙涂料高级外墙涂料,应有出厂合格证、出厂日期及使用说明书。
平米用量根据生产厂家提供的工艺做法确定高级外墙涂料为有关部门鉴定合格的产品,且已经过大量证明效果可靠的产品设专人保管和发放5.弹性腻子弹性腻子,应有出厂合格证、出厂日期及使用说明书平米用量:3~3.5 公斤/平方米6.设备 外墙面砖弹线、挂线所用线绳为细尼龙线勾缝溜子统一加工制作外墙弹性腻子用橡皮与钢皮刮板,外墙涂料大面积采用滚刷,4局部采用毛刷修补主要材料品种及数量等如下表所示:序号 材料名称 规 格 单位 数 量 备 注1 外墙面砖 浅红色 230×53 m2 约11200 详见材料 计划2 瓷砖粘结剂 适用于外墙外保温 t 约 168吨3 瓷砖勾缝剂 加水搅拌即用型 t 约 26吨 勾缝用灰单独 存放4 高级外墙涂料 m2 约13000 5 弹性腻子 t 约 26吨三、施工部署1、进度计划计划于 2007 年 5 月 8 日开始进行外墙装修施工,至 5 月 25 日完成,甲供装修材料必须在外墙装修施工前进场2、作业队伍外墙粘贴面砖和外墙涂料工程由专业施工队伍完成每个单项工程分四个班组,每个班组负责一个楼号各班组在各施工段全面展开施工3、样板制度:各班组在大面积展开施工前,必须实行样板引路制度。
面砖粘5贴完毕和涂料涂刷完毕后由建设单位、监理单位、项目经理部检查验收合格后方可进行大面积施工样板位置设置在项目经理室及门卫外墙上4、垂直运输施工用的砂浆、面砖、腻子、涂料可利用外用电梯进行垂直运输,根据工期要求,视进度情况,必要时采用人工倒运5、施工机械拟采用 2 台强制式砂浆搅拌机,每两部外用电梯旁设置。