9页We will continue to improve the companys internal control system, and steady improvement in ability to manage and control, optimize business processes, to ensure smooth processes, responsibilities in place; to further strengthen internal controls, play a control post independent oversight role of evaluation complying with third-party responsibility; to actively make use of internal audit tools detect potential management, streamline, standardize related transactions, strengthening operations in accordance with law. Deepening the information management to ensure full communication "zero resistance". To constantly perfect ERP, and BFS++, and PI, and MIS, and SCM, information system based construction, full integration information system, achieved information resources shared; to expand Portal system application of breadth and depth, play information system on enterprise of Assistant role; to perfect daily run maintenance operation of records, promote problem reasons analysis and system handover; to strengthening BFS++, and ERP, and SCM, technology application of training, improve employees application information system of capacity and level. Humanistic care to ensure "zero." To strengthening Humanities care, continues to foster company wind clear, and gas are, and heart Shun of culture atmosphere; strengthening love helped trapped, care difficult employees; carried out style activities, rich employees life; strengthening health and labour protection, organization career health medical, control career against; continues to implementation psychological warning prevention system, training employees health of character, and stable of mood and enterprising of attitude, created friendly fraternity of Humanities environment. To strengthen risk management, ensure that the business of "zero risk". To strengthened business plans management, will business business plans cover to all level, ensure the business can control in control; to close concern financial, and coal electric linkage, and energy-saving scheduling, national policy trends, strengthening track, active should; to implementation State-owned assets method, further specification business financial management; to perfect risk tube control system, achieved risk recognition, and measure, and assessment, and report, and control feedback of closed ring management, improve risk prevention capacity. To further standardize trading, and strive to achieve "according to law, standardize and fair." Innovation of performance management, to ensure that potential employees "zero fly". To strengthen performance management, process control, enhance employee evaluation and levels of effective communication to improve performance management. To further quantify and refine employee standards ... Work, full play party, and branch, and members in "five type Enterprise" construction in the of core role, and fighting fortress role and pioneer model role; to continues to strengthening "four good" leadership construction, full play levels cadres in enterprise development in the技术交底记录表C2-1编号工程名称工程交底日期2007年月日施工单位装饰装修工程有限公司分项工程名称一般抹灰交底提要加气混凝土砌块墙面抹灰交底内容:一、适用范围适用于建筑工程加气混凝土砌块内、外墙体抹灰的施工。
二、施工准备(一)技术准备1.编制施工方案,确定施工顺序和方法2.大面积抹灰前做好样板,经监理、建设单位验收合格后,再组织全面施工3.对操作人员进行安全技术交底二)主要材料1.水泥:硅酸盐水泥、普通硅酸盐水泥强度等级不低于32.5严禁不同品种、不同强度等级的水泥混用水泥进场应有产品合格证和出厂检验报告,进场后应进行取样复试水泥的凝结时间和安定性复验合格当对水泥质量有怀疑或水泥出厂超过3个月时,在使用前必须进行复试,并按复试结果使用2.砂:平均粒径为0.35~0.5mm的中砂,砂的颗粒要求质地坚硬、洁净,含泥量不得大于3%,不得含有草根、树叶、碱质和其他有机物等杂质砂在使用前应按使用要求过不同孔径的筛子3.石灰膏:应用块状生石灰淋制,淋制时用筛网过滤,孔径不大于3mm,储存在沉淀池中熟化时间,常温一般不少于15d;用于罩面灰时,熟化时间不应少于30d,使用时石灰膏内不应含有未熟化的颗粒和其他杂质4.磨细生石灰:磨细度过4900目/cm2的筛子,累计筛余量不大于13%用前应用水浸泡使其充分熟化,其熟化时间宜为7d以上5.粉煤灰:抹灰时可使用粉煤灰作为掺合料取代水泥来拌制砂浆,既能节能水泥,又能提高和易性。
最多掺量不大于水泥用量的25%,使用前过0.15mm筛,筛余量不大于8%6.纸筋:白纸筋或草纸筋使用前3周用水浸透并敲打拌合成糊状,要求洁净、细腻,也可制成纸浆使用7.麻刀:柔软干燥,不含杂质,长度约10~30mm使用前4~5d敲打松散,用石灰膏调好8.界面剂:界面剂必须有产品合格证、使用说明书、性能检测报告等质量证明文件进场后及时进行检验,并办理报验其技术性能应符合现行地方标准《建筑用界面处理剂应用技术规程》(DBJ/T 01-40)的规定9.钢板网:钢板网厚度为0.8mm,单个网眼面积不大于400mm2,表面防锈层良好三)机具设备1.机械:砂浆搅拌机、纤维-白灰混合搅拌机、粉碎淋灰机2.工具:铁抹子、压子、塑料抹子、木抹子、阴阳角抹子、捋角器、托灰板、刮杠、八字靠尺板及钢筋卡子、筛子、软水管、软毛刷、钢丝刷、喷壶、水桶、扫帚、锤子、錾子、手推车等3.计量检测用具:磅秤、钢尺、方尺、水平尺、托线板、线坠等4.安全防护用品:口罩、手套、护目镜等审核人交底人接受交底人1.本表由施工单位填写,交底单位与接受交底单位各保存一份2.当做分项工程施工技术交底时,应填写“分项工程名称”栏,其他技术交底可不填写。
技术交底记录表C2-1编号工程名称工程交底日期2007年月日施工单位装饰装修工程有限公司分项工程名称一般抹灰交底提要加气混凝土砌块墙面抹灰交底内容:(四)作业条件1.结构工程已完,并经验收合格2.已测设完室内标高控制线(+0.5m)、外墙水平控制线,并经预检合格3.门窗框安装完,与墙体连接牢固门窗与墙体之间的缝隙用1∶1∶6水泥混合砂浆分层嵌塞密实塑钢、铝合金门窗边框与缝隙处按产品说明书要求的材料嵌填对已安装好的门框采用铁皮或木板加以保护4.墙体内的预埋铁件、螺栓、水电管道和设备等安装完,办理完工序交接手续箱体背面露明部分钉钢丝网,与洞边搭接不得小于100mm5.施工时使用的外脚手架或高凳要提前搭好,架子要离开墙200~250mm,并经验收合格6.抹灰施工前应完成屋面防水层施工三、操作工艺加气混凝土砌块内墙面抹灰一)工艺流程 基层处理→洒水润湿→吊垂直、套方、抹灰饼、冲筋→抹底层砂浆→修抹墙面上的箱、槽孔洞→抹面层砂浆→抹门窗口及护脚→抹踢脚(或墙裙)→养护 (二)操作方法1.基层处理(1)抹灰前检查墙面,剔除松动的和不密实的灰缝砂浆,用掺界面剂的砂浆填塞密实浆墙面的舌头和凸出部位剔平,并清理干净。
加气混凝土砌块缺棱掉角、墙面坑凹不平和水、电管线槽等处用水洇透,刷界面剂一道,随即抹1∶1∶6混合砂浆,分层补齐2)安装在墙体内的各种箱(柜),其背面露明部分需加钉钢丝网,钢丝风与。