土石方回填施工措施.doc
8页1目 录1 工程概况 .....................................................................11.1 工程项目说明 ..............................................................................................................................................11.2 水文气象 ......................................................................................................................................................11.3 工程地质 ......................................................................................................................................................12 施工布置 .....................................................................22.1 施工道路 .....................................................................................................................................................22.2 施工用电 ......................................................................................................................................................22.3 施工排水 .....................................................................................................................................................22.4 取料场规划 ..................................................................................................................................................22.4.1 粘土取料场 .....................................................................................................................................22.4.2 石渣取料场 .....................................................................................................................................32.5 渣场规划 ......................................................................................................................................................33 施工进度安排 .................................................................34 施工方案 .....................................................................34.1 施工程序 .....................................................................................................................................................34.2 施工方法 .....................................................................................................................................................44.2.1 测量放线 .........................................................................................................................................44.2.2 基槽开挖 .........................................................................................................................................44.2.3 刨毛 .................................................................................................................................................54.2.4 铺料平仓 .........................................................................................................................................54.2.5 碾压 .................................................................................................................................................54.2.6 边坡整修 .........................................................................................................................................64.2.7 雨季填筑 .........................................................................................................................................65 资源配置 .....................................................................65.1 劳动力计划 ..................................................................................................................................................65.2 主要施工机械设备配置 ..............................................................................................................................76 质量保证措施 .................................................................77 安全保证措施 .................................................................88 文明施工保证措施 .............................................................81尾水洞工程回填碎石土施工方案1 工程概况1.1 工程项目说明本工程的厂房型式为地面引水式厂房,主厂房尺寸 56.9m×18.3m×40.95m(长×宽×高) ,厂区地面高程为 214.50m,主机间建基高程为 190.85m,尾水渠自尾水管出口以1:4 反坡向下游延伸约 40.0m,然后以 0.2%的坡降与主河道衔接,尾渠两侧设有浆砌石护坡和挡墙。
尾水洞工程的回填碎石土约 10 万 m31.2 水文气象长滩河流域属亚热带湿润季风性气候区,季风明显具有冬无严寒、夏无酷暑,暖湿多雨的特点受清江流域季风气候区的笼罩、且长滩河流域山体比较高大和地形较为复杂的影响,东南暖湿气流受阻抬升,造成长滩河中上游流域内云雾多、湿度大、降水充沛的特点,形成气温自谷地向山地递减、降水自谷地向山地递增的规律性差异根据长滩河流域雨量资料统计,流域多年平均降水量为 1281.5mm;历年年降水量最大值为 1753.6mm,最小值为 912.6mm,二者之比为 1.92本流域地处湖北清江暴雨区和川江暴雨区边缘,洪水由暴雨形成根据把水寺站实测资料分析,洪水主要发生在 6 月~9 月,洪水过程多为单峰,历时约 3 天左右,最大洪量主要集中在 24 小时内,约占 3 天洪量的 50%以上,最大洪峰流量为 1180m3/s(1998 年6 月 29 日) 1.3 工程地质厂区原始地面高程 215.0m~230.0m,地形较平缓,坡度一般为 15°~20°覆盖层厚度一般为 2.6m~5.0m厂房基槽岩体为泥质粉砂岩、粉砂质泥岩互层,强风化岩下限埋深 8.0m~12.0m,中等风化岩下限埋深 38.0m~42.0m。
厂区地下水位高程为210.3m~214.1m厂房基岩节理不甚发育,未见较大的断层破碎带通过,厂房基槽及后山坡稳定性较好2 施工布置根据现场地形和交通条件,本土石方回填工程沿厂房施工区环形布置,土石方回填所用石渣由 6#渣场渣运至回填区22.1 施工道路进厂道路:起于云堰公路,经临建场地,至尾水洞填筑施工区;路宽 7.0m,长500m,最大纵坡 10%主要承担机械设备进场,回填料运输等任务云堰公路:利用既有的云堰公路段作为回填碎石土的施工道路,起于进厂公路,至6#渣场碾压混凝土路面,路面宽 7.0m,长约 750m主要承担石渣回填等任务2.2 施工用电施工用电主要用于尾水洞部位抽排水用电,厂区上部云堰公路旁在 10kv 末端已安装了 1 台 500KNA 变压器,施工用电直接从该变压器低压侧接引至基槽开挖工作面为了保证不间断供电,变压器处配置 1 台 100kw 柴油发电机,作为尾水洞施工的应急电源2.3 施工排水施工期排水主要是施工期间尾。