阿总曲中桥预应力混凝土现浇箱梁施工方案_secret.doc
22页国道 318 线川藏公路海通沟至东达山段整治改建工程 阿总曲中桥预应力混凝土现浇箱梁施工方案I目 录一、工程概况: ......................................................................................................................................1二、主要施工方案及工程量: ..............................................................................................................11、主要施工方案: ........................................................................................................................12、主要工程数量: ........................................................................................................................13、主要施工计划安排 ....................................................................................................................2三、设备、人员配置及施工前期准备 ..................................................................................................21、组织机构框图 ............................................................................................................................22、主要施工设备配置 ....................................................................................................................23、劳动力及人员配置 ....................................................................................................................34、施工前期准备 ............................................................................................................................3四、施工工艺、方法及施工控制重点 ..................................................................................................31、现浇箱梁施工工艺 ....................................................................................................................32、支架预压: ................................................................................................................................53、支座安装: ...................................................................................................................................54、模板安装 ....................................................................................................................................65、箱梁钢筋安装 ............................................................................................................................76、预应力管道安装: .......................................................................................................................87、锚垫板安装: ............................................................................................................................98、预应力筋穿束: ........................................................................................................................99、混凝土浇筑: ..........................................................................................................................1110、砼养护: ................................................................................................................................1211、预应力筋张拉: ....................................................................................................................1212、支架拆除: ............................................................................................................................1613、施工中的控制重点 ................................................................................................................17五、各项施工保证措施 ........................................................................................................................171、质量保证措施 ..........................................................................................................................172、施工管理保证措施 ..................................................................................................................183 安全保证措施 .............................................................................................................................194 环境保护及现场文明施工保证措施 .........................................................................................19国道 318 线川藏公路海通沟至东达山段整治改建工程 阿总曲中桥预应力混凝土现浇箱梁施工方案1阿总曲中桥预应力混凝土现浇箱梁施工方案一、工程概况:本桥孔径跨径组合采用 3×20 米。
桥面宽度:标准断面为 0.5m(防撞护栏)+8m(车行道)+0.5m(防撞护栏) , ,箱室断面均为单箱三室桥梁平面布置:本桥平面在 K3520+044.107 前位于 R=133.05m 的圆曲线内、之后位于缓和曲线段,墩台径向布置;纵面位于竖曲线段,变坡点桩号K3519+828(标高 3714.889m,R=1700m) 、 K3519+982(标高3725.566m,R=1800m) 、K3520+095(标高 3730.565m,R=1400m ) 二、主要施工方案及工程量:1、主要施工方案:现浇箱梁施工支架采用碗扣式满堂脚手架支撑,满堂脚手架地基采用 5%灰土处理 50cm 厚,灰土顶面作好排水坡(双面或单面排水)并用塑料膜封面防水底模采用 1.5cm 光面竹胶板,侧模采用定型钢模,芯模采用竹胶板钢筋由现场加工制作后,在底模上绑扎成型混凝土采用现场搅拌,人工运至施工作业点浇筑,插入式振动棒捣固混凝土强度达到设计强度的 90%且混凝土龄期不小于 7 天,方可进行预应力张拉施工2、主要工程数量:现浇箱梁主要工程数量表桥梁名称 单位 数量 备注 阿总曲中桥 跨 3 现浇箱梁 C50 混凝土总方量为:332.7m 3国道 318 线川藏公路海通沟至东达山段整治改建工程 阿总曲中桥预应力混凝土现浇箱梁施工方案23、主要施工计划安排现浇箱梁施工:计划于 2011 年 3 月 15 日开始,2011 年 6 月 25 日结束。
三、设备、人员配置及施工前期准备1、组织机构框图 项 目 经 理 杨 传 国总 工 程 师 余 颖 副 经 理惠 文 斌 韦 建 国质 量 安 全 科 韦 建 国 物 资 装 备 科 惠 文 斌 办 公 室徐 东 平工 地 试 验 室将 祖 龙 现 浇 箱 梁 施 工 队工 程 技 术 科 田 志 文 财 务 科张 保 旺项 目 书 记何 东 学2、主要施工设备配置根据设计要求,本工程选用的设备型号及具体数量如下表:序号 设备名称 规格及型号 单位 数量 备注1 发电机 100Kw 台 12 挖掘机 PC200 台 13 空气压缩机 W-285/5 台 44 钢筋切断机 FGQ-40 套 25 钢筋弯曲机 GJ7-40 套 27 钢筋调直机 GTJ4-4/14 套 27 电焊机 BX2-500 台 68 振动捧 台 109 千斤顶 250t 台 410 真空压浆机 HB-3 台 111 真空压浆泵 MBV-80 型水环式 台 1@nts。