37页万州区苎溪河库岸综合治理 4#护坡、挡土墙和土石方回填单位工程验收工程施工管理工作报告重庆恒杰建筑安装工程有限公司二〇一〇年十一月 批审校编准:查:核:写: 目录1.工程概况···································································································32.工程投标···································································································53.施工总布置、总进度和完成的主要工程量··········································84.主要施工方法·························································································125.施工质量管理·························································································186.文明施工与安全生产············································································277.价款结算与财务管理·············································································298.经验与建议·····························································································30 9.附件·········································································································311工程概况1.1地理位置及工程简介1.1.1地理位置万州区苎溪河库案综合治理工程 4#地段,位于万州区北滨路长江制药厂外侧,库岸线长约 800多米,东起 318国道关塘口段,西至老万一桥场地中部靠苎溪河万州新大桥与天子路万开路相通。
万州区苎溪河库案综合治理工程 4#地段工程分为一、二两个治理阶段,高程 160.3米以下工程是一期治理工程,现已基本完成高程 160.3米至 177.3米 段工程属二期治理项目1.1.2主要工程项目及工程量根据施工合同(合同编号:冠荣工合 09-07-15)的规定,万州区苎溪河库案综合治理工程 4#地段工程内容包括:护坡、挡土墙、土石方回填施工1.1.3完成工程量对比情况见表完成工程量一览表序号1实际完成工程量72.889611项目单位概算工程量合同工程量备注3夹石土回填堆石回填万m约约约约32万mm333805碎石垫层4m34120干砌条石护坡干砌砼六棱块护坡567m3m3m15861100186约约约C20钢筋砼底板4-1排水沟的砌筑4-1砖砌体保护高架桥结构89m3125.9250约约约3m棱柱体的补砌13-15段原始地万m3104.5954貌夹石土回填1.1.4工程投资及工期本单位工程计划投资总额为 24502843.78元,合同投资金额为按实结算,实际完成投资金额为 20000000.00万元本单位计划开工日期: 2009年 7月 6日,竣工日期: 2009年 12月30日,实际竣工日期: 2010年 11月 23日。
1.2气象及水文本工程所在地属亚热带季风气候,具有四季分明、雨热同季的特点多年平均气温 20℃,最高气温 40℃,最低气温零下 5℃;无霜期多年平均在 300天左右;多年平均降雨量 1169mm,最大年降雨量 1408mm;多年平均日照时数达 1800~2100h;最大风速达 4m/s,汛期多年平均最大风速 15m/s;洪水汛期为 5~10月份,主汛期为 7~9月份由于本工程施工期间雨水偏多,年初汛期提前进入,给施工带来了一定的难度引水总干渠加固工程施工期雨天统计情况见表 1.2.1表 1.2.1施工期雨天统计表月份123456789101112雨天年份200920101.3工程地形地质1.3.1地质条件经勘察,本工程区域内属多层结构土体类型在低山丘岗、堆积岗波状平原区和冲洪积三级阶地区发育中更新的老粘性土,具有低压缩、隔水性好、强度较高的特点,地质条件较好1.3.2天然建筑材料本工程所用砂、石料源于长江砂石料场,是优质的砼浇筑用料及垫层用料,用自卸车运至施工现场,运距为 15km;水泥为万州科华水泥厂普通硅酸盐 32.5水泥,用汽车运至施工现场运距为 25km;块石为申 明坝料场,岩石质地坚硬,是优质的护砌石料,用自卸车运至施工现场,运距为 20km。
1.4工程等别及特点1.4.1工程等级工程设计边坡安全等级为一级,堤防等级为 4级1.4.2工程标准22建筑物房屋层数 2-7层,以 30KN/M -15KN/M计算,场地及公路荷载按《建筑结构荷载规范 GB500》4.1条规定1.4.3、工程规模万州区苎溪河综合治理工程 4#地段单位工程主要建设内容包括:2,(1)护岸夹石土的回填:面积约 80000多 m,填筑深度为 10-15米2)护岸堆石回填碾压:护岸堆石回填碾压库岸线全长约米,填筑深度 10-15米,填筑宽度 14-16米2工程投标800多2.1标前准备2009年 6月 10日,本公司接到重庆冠荣房地产开发有限公司委托重庆渝强招标代理有限公司总裁发出的投标邀请书后,立即组建专门的投标机构,抽调有标书编制经验的技术骨干组成了编标小组2009年 6月 15日,本公司组织有关技术人员对施工现场进行踏勘并召开标前会,对施工现场进行全面的考察,收集所有可收集到有关本工程的资料,为编制投标文件及今后进场施工做好了充分的准备2.2标书的编制依据(1)万州区苎溪河综合治理工程 4#地段单位工程施工招标文件,施 工图纸及补充函;(2)国家部委和地方有关政策法规;(3)《水利水电工程施工设计概 <估>算定额》;(4)《水利水电建筑工程概算定额》,缺项部分套用其它行业相关定额;(5)《水利水电工程施工机械台班费定额》。
2.3施工组织设计编制的原则(1)遵照招标文件中合同条款的各项要求,实质性的响应建设单位及监理单位的指令和要求的原则;(2)施工严格遵照招标文件明确的设计规范、施工规范与验收标准的原则;(3)坚持在实事求是的基础上力求先进、科学、合理、经济、实用的原则;(4)坚持自始自终的施工现场全过程严密监控,以科学的方法实行动态管理的原则;(5)采用先进的施工工艺、施工技术、制定科学施工方案的原则;(6)以标书中的各项说明为预期和行动纲领,坚持言必行、行必成的原则2.4施工组织设计编制的依据(1)万州区苎溪河库岸综合治理工程 4#地段单位工程施工招标文件,施工图纸及补充函;(2)《水利基本建设工程验收规程 <试行>》SD184-86;(3)《堤防工程施工质量评定与验收规程 >》SL239-2008;(4)《堤防工程施工规范》 SL260-98;(5)《水利水电建设工程验收规程》 SL223-1999; (6)《堤防工程设计规范》 GB50286-98;(7)《水利水电工程测量规范》 DLJ202-81、SLJ3-81;(8)《水利水电工程施工测量规范》 SJ52-93;(9)《水利水电工程天然建筑材料勘察规程 <试行>》SDJ17-78;(10)《水利水电工程施工地质规范 <试行>》SDJ18-78;(11)《碾压式土石坝施工技术规范》 SDJ213-83;(12)《水利水电工程施工组织设计规范》 SDJ338-89;(13)《建筑地基处理技术规范》 JGJ79-91;(14)《砌体工程施工及验收规范》 GBJ501D4-66;(15)《砖石工程施工及验收规范》 JBJ203-83;(16)《硅酸盐水泥、普通硅酸盐水泥》 GB175-1999;(17)《混凝土拌合楼 <站>用搅拌机》 DLJT456-91;(18)《水工混凝土施工规范》 SDJ207-82;(19)《预制混凝土构件质量评定标准》 GBJ321-90;(20)《施工现场临时用电安全技术规范》 GBJ232-82;(21)现场踏勘收集到的资料、工程特点、现场客观条件。
2.5开标、中标与签订施工承包合同2009年 7月 4日上午 9时,由万州区水利厅组织有关单位在重庆渝强招标代理有限公司对本工程进行了公开开标经评标委员会委员们的评审,最终推荐我公司为万州区苎溪河库岸综合治理工程 4#地段单位工程中标单位,并以形式发出中标通知书我公司在接到中标通知后由总经理邓小军、项目主管吕传富、项目经理罗大华强在2009年7月 5日,对施工合同进行最后商定,随后签署了万州区苎溪河综合治理工程 4#地段单位工程施工合同协议书与其它相关合同 3施工总布置,总进度和完成的主要工程量3.1施工总体布置3.1.1布置原则(1)科学合理地安排施工现场和各种设施,满足各项目、各工序的衔接及施工方便2)在业主提供的用地范围内进行合理规划,本着合理、必须的原则,尽可能减少占地3)油料库、危险材料仓库的布置与结构遵守国家安全防爆、防火等规范要求4)临时卫生设施要认真规划,污水、污物的处理要符合相关规定的要求3.1.2水、油、电系统的布置本工程施工用水用水泵直接从苎溪河抽至施工现场的蓄水池中澄清后使用,水质优良施工现场有排水沟,利用自流自然排水生活用水搭接建设单位机关自来水。
施工机械用油料:机油、汽油、柴油均由施工单位从万州采购运至工地施工及生活用电均搭接建设单位机关所在地电网,共搭接 1处3.1.3混凝土搅拌系统的布置3本工程混凝土主要以护坡、钢筋砼底板、 4-1排水沟共 1100m因此,混凝土搅拌系统必须布置在适合施工的部位根据施工进度,。